Drop Kerb Installation

Client

Private

Location

Reynolds Drive, Lincoln

Duration

2 Days

Description

Work here included:

  • Chapter 8 supplied
  • Signs and barriers
  • Excavation of agreed area to 200mm
  • Removal of existing kerbs
  • Installation of two tapered kerbs and three drop kerbs
  • Import of 100mm of type 1 MOT road stone (compacted)
  • Import and lay of 70mm of 20mm base course tarmac
  • Import and lay of 30mm of 6mm tarmac
  • Clean site and tidy