Client
Private
Location
Reynolds Drive, Lincoln
Duration
2 Days
Description
Work here included:
- Chapter 8 supplied
- Signs and barriers
- Excavation of agreed area to 200mm
- Removal of existing kerbs
- Installation of two tapered kerbs and three drop kerbs
- Import of 100mm of type 1 MOT road stone (compacted)
- Import and lay of 70mm of 20mm base course tarmac
- Import and lay of 30mm of 6mm tarmac
- Clean site and tidy