Bio Gas Installation, Blackpool

Client

UCPCHOICE

Location

Blackpool

Description

Bio gas installation at Amy Johnson Way Industrial estate Blackpool.

Integral utility services ltd are proud to show you our 1.2 kilometre trackwork project just completed at Blackpool for our client UCPCHOICE.

The project was for a new bio gas installation and consisted of excavation in footpath and C/W with a track over 1.1m wide and 1m Deep to accommodate 2 HV cables and one I.P Gas main.

We can happily say the project was completed with no incident or even one utility strike......

That said it did come with certain challenges with the route being so close to the Blackpool beach and seasonal weather changes.

The whole route was foam concreted at the local council’s request and involved many sections to be completed with nightwork to maintain the busy daily flow of vehicles to the thriving industrial estate.

Thank you, Tony and your team for a successful project. Keep up the good work.