T: 01522 275 069

E: info@integralutilityservices.co.uk

Menu

IUS Projects

DNO Substation built for Elton Solar Farm

Client

UCPC, Balfatech

Location

Elton, Newark

Duration

5 Weeks

Description

DNO Substation built in approximately 5 weeks for clients Balfatech/UCPC as part of a 10MW Solar farm in Elton (Nottinghamshire)

The build included...

  • All excavation and waste disposal.
  • All earthing and low voltage electric installation.
  • Roof and drainage installation.
  • Concrete footings and plinth work.
  • Concrete blockwork outside and inside.
  • Coloured Rendering.
  • All fixtures and fittings.
  • Gravel footpath and concrete installation pad outside main doors.
  • The substation was completed 1 week ahead of schedule and was also part of a 3000m underground excavation scheme 'Integral utilities ltd' also undertook and successfully completed SAFELY and with no incident or complaint,(Further post and pictures to be updated).
« Back to Latest Projects