3KM Track Work for Elton Solar Farm, Newark

Client

UCPC, Balfatech

Location

Elton, Newark

Duration

10 Weeks

Description

  • 3000m 33KV track and cable installation at Elton, Newark for 10MW solar farm
  • This work was completed one week ahead of schedule
  • Completed safely with no incident or complaints
  • Work included excavation in grass verges, agricultural land, and carriageway.